SharonAI Holdings, Inc.: Miss — EPS -$1.14, Revenue $9.93M

SHAZSharonAI Holdings, Inc.•Q3 2026•Nov 16, 2026, 4:05 PM EST
1
Earnings MissQ3 2026 · After-market

Did SharonAI Holdings, Inc. (SHAZ) beat earnings today?

@trystockwhiz

No, SharonAI Holdings, Inc. (SHAZ) missed Wall Street analyst expectations for Q3 2026, reporting lower-than-expected EPS and lower-than-expected revenue.

Earnings Per Share-103.57% surprise
-$1.14Actual
Expected: -$0.56
vs. year ago -570.6%
Total Revenue-63.25% surprise
$9.93MActual
Expected: $27.02M
vs. year ago +1859.0%
Released Nov 16 · 4:05 PM ET

Earning Report

MetricQ3 2026Q3 2025YoY Change %
Revenue$9.93M$506.75K+1859.0%
Net Loss($43.79M)($1.64M)-
GAAP Basic/Diluted EPS-$1.14-$0.17-

Financial Outlook / Guidance

January 2027 Outlook

ARR
Guidance
$400-$450M
Total Capacity
Guidance
—
Available Capacity
Guidance
—

2027 Outlook

ARR
Guidance
—
Total Capacity
Guidance
212MW
Available Capacity
Guidance
~155MW

Business Highlights

  • ➤Power is onsite at all contracted customer data-center sites across Australia and New Zealand.
  • ➤Delivered and achieved customer acceptance for an approximately 1,000 NVIDIA B300 GPU cluster.
  • ➤Signed a five-year Rafay Systems agreement to orchestrate up to 150,000 GPUs.
  • ➤Collaborated with VAST Data on the launch of DataEnclave.
  • ➤Added 80MW of incremental capacity in Australia.
  • ➤Achieved data-center energization for NVIDIA B300 and GB300 clusters; commissioning and NVIS verification are underway.
  • ➤Achieved SOC 2 Type 2 attestation.
  • ➤Appointed Anuj Goel as Chief Financial Officer.
  • ➤Appointed Melissa Anastasiou as Chief Legal Officer.
  • ➤Appointed David Burns as Chief Operating Officer; Andrew Leece became Head of Strategic Partnerships.
  • ➤Appointed Guy Wylie as Head of Capital and Strategy.

Management Commentary

Anuj Goel, Chief Financial Officer

“Since December 2025, Sharon AI has secured approximately $2.6 billion of capital, including our inaugural GPU-backed facility valued at $356m, establishing a repeatable financing structure supported by customer contracts,”

Anuj Goel, Chief Financial Officer

“Further GPU-backed facilities to fund the next stage of the build-out are well advanced. The market remains open and highly interested in our secured GPU-backed debt which we intend to raise against signed take-or-pay contracts, secured against the GPUs dedicated to them. The majority of our TCV(1 )is with customers that hold investment-grade credit ratings, and we expect greater than 75% of our aggregate secured debt packages to stem from the NVIDIA AI Compute Program.”

James Manning, Co-founder and Chief Executive Officer

“In the third quarter, we advanced the conversion of our contracted commitments into live AI infrastructure at scale, delivering and achieving customer acceptance of the initial deployment for our global technology customer,”

James Manning, Co-founder and Chief Executive Officer

“We also achieved SOC 2 Type 2 attestation, an important security and compliance milestone. ”

James Manning, Co-founder and Chief Executive Officer

“Globally, demand for AI compute is outpacing the power available to deliver it, and this is where Australia, and Sharon AI, stand apart. Our TCV(1) has increased to ~$9.6 billion over 5.5 years(2), with this TCV only including the floor price of the NVIDIA AI Compute Program for ~40,000 NVIDIA GB300s online in 2027. ”

James Manning, Co-founder and Chief Executive Officer

“Over the course of 2026 we have seen pricing on our long-term contracts strengthen from ~$15 million to more than $19 million annualized revenue per MW, with new customer prepayments at up to 30% of TCV or 60% of capex. In relation to the NVIDIA AI Compute Program, we expect to sign shorter-duration contracts at over $30 million annualized revenue per MW. ”

James Manning, Co-founder and Chief Executive Officer

“With power in place, we are executing on delivery alongside our deployment partners, and that is our focus in the fourth quarter and beyond. We expect to complete commissioning, testing and NVIS verification of the ESDS and global technology customer deployments in December 2026 and January 2027, taking ARR(3) from approximately $50 million for September 2026 to an anticipated $400-450m ARR(3) for January 2027, with our additional deployments, including the NVIDIA AI Compute Program, following through 2027. With a strong long-term contracted customer base, live deployments and ~155MW(4) of capacity available for sale, strengthening short and long-term GPU pricing and access to institutional capital, we are building a leading sovereign AI compute platform at increasing scale across Australia and New Zealand.”