AZIO AI Confirms Atlas One Texas AI Compute Campus Is Designed to Run Fully Off the ERCOT Grid
Key Highlights
- ➤Atlas One designed to operate fully off the ERCOT grid
- ➤Texas weighs 474 gigawatts of interconnection requests, 90% from data centers
- ➤Power Champion agreement covers 10 MW at $150 per kilowatt monthly
- ➤Planned Phase One capacity totals 11 MW, not yet fully energized
- ➤Atlas One generation requires air authorization and other permits before energization
Expert Statements
Elgin Tracy, Chief Operating Officer of AZIO AI Holdings, Inc.
“Texas is not turning against data centers. It is turning against data centers that expect everyone else to carry their costs and their risk.”
Elgin Tracy, Chief Operating Officer of AZIO AI Holdings, Inc.
“We are not waiting in a 474-gigawatt line, and we are not asking Texas ratepayers to fund a new substation. Behind-the-meter is not a loophole. The closer a project is to being self-supplied, the less it depends on policy decisions that are now in flux.”
Elgin Tracy, Chief Operating Officer of AZIO AI Holdings, Inc.
“Texas now asks for proof of site control, financial commitment and real data. That favors developers who build in sequence over those who announce gigawatts first.”
Elgin Tracy, Chief Operating Officer of AZIO AI Holdings, Inc.
“We would rather build a business that holds up under stricter rules than one that depends on loose ones, and be straight with regulators and investors about what is done and what is still ahead.”
HOUSTON, Nov. 10, 2026 (GLOBE NEWSWIRE) -- AZIO AI Holdings, Inc. (Nasdaq: AZIO) ("AZIO" or the "Company") today confirmed that Atlas One, the first Project Atlas campus, in Live Oak County, Texas, is designed to run fully off the ERCOT grid, with no pending ERCOT large-load interconnection request.
The confirmation comes as Texas tightens the path onto its grid. According to the Office of the Governor, ERCOT is weighing roughly 474 gigawatts of requests to connect, more than five times the state's record peak demand, and about 90 percent of that is data centers.