Duke Energy protects customers from data center costs

PR Newswire•07/10/2026•15:54 ET
0

Key Highlights

  • ➤Duke Energy settlement shields existing customers from data center service costs
  • ➤New customers 50 megawatts or more face upfront payments, deposits and guarantees
  • ➤High Load Factor rates required for new large-load customers, including data centers
  • ➤North Carolina Utilities Commission approval expected by mid-November
  • ➤Duke Energy Carolinas and Duke Energy Progress combine into one utility January 1, 2027

Expert Statements

Kendal Bowman, Duke Energy's North Carolina president

“It's simple – data centers will pay upfront for all costs to connect to the grid”

Kendal Bowman, Duke Energy's North Carolina president

“We're shielding other customers from these costs in a way that protects reliability and ensures everyone benefits from the economic growth coming to North Carolina.”

Duke Energy protects customers from data center costs PR Newswire

* Agreement with North Carolina Public Staff, Amazon, Google, Meta, Microsoft and others enhances existing protections to further insulate customers from data center costs while delivering billions in long-term benefits CHARLOTTE, N.C., Oct. 7, 2026 /PRNewswire/ -- Duke Energy and stakeholders have reached an agreement that further protects existing customers from costs to serve data centers and other large-load customers in North Carolina.