ICE Launches New Tool to Quantify Data Center Construction Risk

Business Wire•17/11/2026•08:30 ET
1

Key Highlights

  • ➤ICE launches Data Center Site Analytics Tool across 3,100+ U.S. counties
  • ➤Construction disruption model achieved 77% accuracy against historical permit outcomes
  • ➤Median $2.7B project delays could cost $162M-$270M over 12 months
  • ➤Tool analyzes 47 geospatial layers covering permits, site characteristics, and markets
  • ➤Global data center spending projected to reach $7T by 2030

Expert Statements

Larry Lawrence, Head of the Geospatial Intelligence team at ICE

“Data center capital is moving faster than local permitting and community consensus, and that gap is now a material financial risk”

Larry Lawrence, Head of the Geospatial Intelligence team at ICE

“On a median-sized $2.7 billion project, a 12-month delay can cost $162 million to $270 million, so giving developers and communities a common, data-driven view of those costs can lead to better-informed agreements.”

ICE Launches New Tool to Quantify Data Center Construction Risk

Intercontinental Exchange, Inc. (NYSE: ICE), one of the world's leading providers of financial market technology and data powering global capital markets, today announced the launch of the ICE Data Center Site Analytics Tool. The tool helps developers, investors, lenders, and municipalities assess the feasibility and delay risk of data center projects before capital is committed.